Skip to content

Orion Pipeline (Dormant)

Overview

PennEast Pipeline Co. Proposes 114-mile Large Scale Natural Gas Transmission Line Through the Delaware River Basin. 

PennEast has been improperly accessing properties for purpose of surveys.  See their letter and our response.

The PennEast Pipeline project is being proposed by AGL Resources, NJR Pipeline which is a subsidiary of New Jersey Resources, South Jersey Industries, UGI PennEast which is a subsidiary of UGI Energy Services, PSEG Power, Spectra Energy Partners.

The project, as proposed, will cut through Luzerne County, PA, Carbon County, PA, Northampton County, PA, Bucks County, PA, and Hunterdon County, NJ Proposed  The company has created a searchable map if you want a more detailed look at the proposed route: PROPOSED ROUTE

Learn About Pipelines:

Information about pipelines, including research, reports and video interviews with experts, can be found at: www.stopthepipelines.org

Learn about all the natural resources and preserved lands PennEast will cut on its way from start to finish.  Fact sheet here.

Delaware Riverkeeper Network comments, copies of township resolutions, and additional information regarding PennEast can be found below.

Project Details: 

The PennEast Pipeline Co. L.L.C. announced its new pipeline project on August 12, 2014 called the PennEast Pipeline. The Federal Energy Regulatory Commission (FERC) granted approval for the project (a Certificate of Public Convenience & Necessity) on February 20, 2018.  PennEast quickly began demanding that property owners who had not yet signed access agreements with the company either do so or receive a lower payment for the property rights the company would ultimately be taking.  Actions for eminent domain have been filed by PennEast against well over 100 properties. (NJ eminent domain actions are listed here; PA eminent domain actions are listed here) .  Among the properties targeted are those in which states have property interest.  In the State of New Jersey the state has property interests in a reported 42 parcels that PennEast is targeting.  New Jersey resisted PennEast’s exercise of eminent domain over these parcels in which the state has property interest and rights.  In a decision issued on September 10, 2019 titled In re PennEast Pipeline Company LLC the U.S. Court of Appeals for the Third Circuit determined that PennEast did not have the right to exercise eminent domain over these parcels as to do so was an infringement on the sovereign immunity of the state.  In response, on October 4, 2019, PennEast filed Docket No. RP20-41 urging FERC, after only an 8 day comment period, to issue a declaratory order that rejected the Third Circuit’s interpretation.  

To date regarding reviews and approvals:

  • On April 26, 2017 the New Jersey issued a determination that the PennEast application materials submitted to the state were significantly deficient and incomplete. On June 28, 2017, NJDEP determined the PennEast Pipeline Company’s application for state approval of its project to be “administratively closed” due to the company’s failure to remedy significant identified deficiencies and its failure to provide full information in a timely fashion for Clean Water Act decisionmaking.  On August 4, 2019 PennEast submitted a renewed application for a state Freshwater Wetlands Act permit, a Flood Hazard Area Verification and Letter of Interpretation, and a Clean Water Act Section 401 Certification.  On October 8, 2019, NJDEP denied the applications without prejudice (leaving the door open for PennEast to re-file if they so chose). 
  • The DRBC has not issued a docket, necessary for the project to move forward, nor has it scheduled hearings on a docket proposal.   The Delaware Riverkeeper Network has issued a petition regarding DRBC jurisdiction over the project and its roll in preventing tree felling or clearing prior to approval which can be read here.
  • The Army Corps of Engineers has yet to issue permits for the project.
  • Pennsylvania has issued Clean Water Act 401 Certification for the project, a decision the Delaware Riverkeeper Network is challenging in court.  But has not issued the underlying permits.The Army Corps has not fully signed off on the project with permits.  

The PennEast Pipeline is designed to be a large scale 36 inch transmission pipeline that will stretch 108 miles from a gathering system in Luzerne County and terminate at Transcontinental Gas Pipe Line Co.’s Trenton-Woodbury Lateral in Mercer County, N.J. The proposed project is planned to transport roughly 1 billion cubic feet of natural gas per day. The project will also require the siting and construction of multiple high-powered compressor stations scattered along the line. 

The PennEast Pipeline Project will cut its right-of-way for over 114 miles approximately 87% of which will be within the boundaries of the Delaware River watershed.  Among the waterways to be crossed are the Delaware, Lehigh and Susquehanna Rivers. Among the federally listed species already identified that could be impacted by the project are the Bog Turtle, the Indiana Bat, the Dwarf Wedge Mussel and the Northern Long-eared Bat which has been proposed-for-listing. Also targeted are forests as well as public and private lands, much of that land being sensitive green fields that have not previously been disturbed. 

The pipeline will affect approximately 1,094 tracts of land and approximately 861 landowners. Eleven municipalities have already passed resolutions opposing the pipeline including: Hopewell Twp, Delaware Twp, Holland Twp, West Amwell Twp, Lambertville, Alexandria, Milford, Princeton, Clinton Twp, Kingwood Twp, NJ and Moore Twp, PA. 

Size and Scope 

The size and scope of the construction activity for the PennEast line and stream crossings associated with this project will have a deleterious effect on the water resources of the Delaware River Basin. Large scale transmission lines such as the PennEast line also result in significant forest fragmentation, invite and propagate the spread of invasive species, and degrade the diversity and dispersion of native flora and fauna. Furthermore, pipeline projects also degrade the functions and values of the wetlands that they plow through, as the construction and operation of the pipeline permanently converts forested wetlands to uplands or emergent wetlands. 

There are also significant concerns related to the cumulative impacts of the continuous water crossings and wetlands disturbance that pipeline construction activity has on the health and vitality of the Delaware River Basin. This is particularly a concern with the PennEast line, as many of these same subwatersheds were recently impacted by construction activity on Transco’s parallel line. Also, in addition to the Transco’s previous and proposed pipeline projects, there are several other pipeline projects that have been concentrated in the same sub watersheds as the PennEast line, such as: Texas Eastern’s TEAM 2014 Project and Columbia’s East Side Expansion Project. 

The PennEast Pipeline will further facilitate the development of new gas drilling wells, access roads, gathering lines, compressor stations, and other supporting infrastructure, which will further degrade our environment. The PennEast line will need to receive a number of important federal and state permits and authorizations for it to proceed. This includes authorizations from the Federal Energy Regulatory Commission (Docket CP15-558), the Army Corps of Engineers (Section 404 permit), the Pennsylvania Department of Environmental Protection and New Jersey Department of Environmental Protection (Section 401 Clean Water Certifications). 

This fall 2019, we’re sending that message to DRBC in a big way with escalating actions that are easy for you to join from near or far, and that will culminate in a big turnout at the DRBC’s December 11 meeting.

Updates:

March 18, 2020: Delaware Riverkeeper Network sends letter urging DRBC transparency and to remain strong and vigilant on PennEast. 

September 10, 2019: The U.S. Court of Appeals for the Third Circuit, in In re PennEast Pipeline Company LLCm determined that PennEast did not have the right to exercise eminent domain over land parcels in which the state of New Jersey had property interests and was refusing access. The court said that the exercise of eminent domain over these parcesl would be  an infringement on the sovereign immunity of the state.  In response, on October 4, 2019, PennEast filed Docket No. RP20-41 urging FERC, after only an 8 day comment period, to issue a declaratory order that rejected the Third Circuit’s interpretation.  

October 1, 2019: Just 3 days before the US Court of Appeals for the DC Circuit was to hear oral argument on the case brought by the Delaware Riverkeeper Network and others to challenge the FERC certificate issued to the PennEast pipeline the court placed the case in abeyance for an undetermined period of time.

March 19, 2019: U.S Court of Appeals Grants Motion for Stay on PennEast Pipeline: “In the event [PennEast] transitions from the surveying and testing phase to the construction phase of the pipeline project, physical construction of the pipeline shall be stayed pending this appeal.”

February 16, 2019:PADEP noticed its call for public comment.  DRN requested a comment extension and submitted Comments to the DEP, which can be found here.

February 15, 2019: PennEast is Modifying Its Proposed Route.  March 8, 2019 is the deadline for Intervening in the FERC Process for the PennEast Pipeline Project Application for Amendment.  In addition, the Pennsylvania DEP is seeking comment on its proposal to approve PennEast as being in compliance with state water quality standards.

On February 15, 2019, the Federal Energy Regulatory Commission (FERC) issued a Notice of Application for Amendment (“Notice”) regarding the PennEast Pipeline Company, LLC’s (PennEast) application under section 7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission’s regulations to amend the certificate of public convenience and necessity and related authorizations issued by the Commission on January 19, 2018. The proposed modifications to the PennEast Pipeline include a series of route realignments and adjustments in Luzerne, Carbon, Monroe, and Northampton Counties, in Pennsylvania. The Notice invites the public to provide motions to intervene before March 8, 2019 at 5:00 pm.

You can find the notice here and PennEast’s Application for Amendment here.

Intervening on a project that has been filed for approval with FERC is important and valuable:  it shows how strongly you are opposed to a project, it preserves your rights to bring a legal challenge should you wish to do so down the road, and it ensures you will be fully informed about every step of the process as it goes forward through email notifications. Click HERE for step by step instructions on how to intervene online with FERC for PennEast’s application to amend their certificate.

August 13, 2018:On Friday, August 10th, The Federal Energy Regulatory Commission denied the rehearing request from the Delaware Riverkeeper Network, NJDEP and others. In reply, on August 13, the Delaware Riverkeeper Network filed with the D.C. Circuit Court of Appeals challenging the FERC approval of the PennEast pipeline claiming the agency violated the Natural Gas Act and the National Environmental Policy Act when it granted approval of the pipeline.

Read the articles for more information:
FERC sued over PennEast approval after denying rehearing requests | StateImpact PA | 2018-08-13
FERC Rebuffs Requests to Reconsider Approval of PennEast Pipeline | NJ Spotlight | 2018-08-13

May 30, 2018: FERC denied the Delaware Riverkeeper Network’s requests for rehearing from the February 22 request. Commissioner Glick wrote a concurrence highlighting the need for the FERC Commission to act on Rehearing Requests as quickly as possible so as to avoid “needless and avoidable harm” to “landowners, communities, and the environment.”

DRN is committed to restoring natural balance in the Delaware River and watershed where it has been lost and ensuring preservation where it still exists. As such, we are actively engaged at the local, state, and federal government levels to ensure that full weight of legal environmental protection laws are brought to bear on all pipeline projects under consideration, including the PennEast Pipeline.

May 8, 2018: Delaware Riverkeeper Network initiates two legal actions to stop construction of Penneast pipeline in the D.C. Circuit Court of Appeals. One is challenging Penneast’s Certificate of Convenience and Necessity and includes a Petition for a Writ of Mandamus to stop construction of the pipeline. The other case challenges FERC’s continued abuses of tolling orders.

April 13, 2018: FERC issues a second order tolling the second rehearing request submitted by Delaware Riverkeeper Network on February 22.

February 22, 2018: Delaware Riverkeeper Network submits a second rehearing request. This one for the tolling order issued for the initial hearing request on February 22.

February 22, 2018: Delaware Riverkeeper Network’s first rehearing request is tolled by FERC. To learn more about FERC’s abuse of tolling orders in these instances see DRN’s Dossier of FERC Abuses.

February 15, 2018:Delaware Riverkeeper Network petitions the Delaware River Basin Commission (DRBC) to exercise its authority in the Delaware River Basin; ensure a nonpoint source pollution control plan is secured, reviewed, and approved for Penneast prior to approval of a DRBC docket; and ensure the DRBC will prevent construction on any part of the Penneast pipeline until Commissioner approval of a DRBC docket for the project.

February 6-13, 2018: PennEast commences almost 200 eminent domain actions in U.S. District Courts in New Jersey and Pennsylvania.

January 24, 2018: Delaware Riverkeeper Network submits its first Rehearing Request to FERC and a Motion for Stay to halt construction of any land disturbance project associated with the pipeline.

January 19, 2018: FERC issues Certificate of Convenience and Necessity with a 4-1 vote. The Certificate included two concurrences and a dissent. Commissioner La Fleur and Commissioner Chatterjee wrote separate concurrences to highlight the issue of how pipeline developers engage with landowners. Commissioner Glick wrote a dissent highlighting and criticizing FERC’s allowance of contracts among affiliates to show need and the practice of FERC conditionally granting Certificates due to lack of evidence of environmental harms.

March 2, 2016 the Delaware Riverkeeper Network filed a Constitutional Challenge to the FERC process as it applies ot the PennEast project. While the court determined that DRN has met the bar for purposes of standing (an important precedent), the case was ultimately dismissed.  DRN is appealing.  

April 2016: responding to an effort led by the Delaware Riverkeeper Network that was supported by over 6,000 individuals, DRBC announced its intent to hold independent hearings.

Where PennEast Proposes to Cut Under the Delaware River
Where PennEast Proposes to Cut Under the Delaware River

September 2014: the Delaware Riverkeeper Network submitted a formal petition to the Delaware River Basin Commission (DRBC) requesting the agency take jurisdiction over the proposed PennEast pipeline project; DRN also crafted an action alert calling for letters from the public which has resulted in the submission of well over 500 citizen letters. Initially DRBC resisted jurisdiction, but follow-up letters from the Delaware Riverkeeper Network along with a deliberate press strategy and growing public pressure finally convinced the agency otherwise. The DRBC has made the decision to exercise jurisdiction over the project.  DRBC has the authority to stop PennEast if it so chooses.