Comment by Monday, December 21
LNG (liquefied natural gas) export plants are massive industrial sites that process methane gas into a liquid, store it, and load it onto ships, primarily for export. Right now, the federal agency that approves them, the Federal Energy Regulatory Commission (FERC), is required to examine each expansion before it’s built. FERC wants to change that.
What FERC wants to do
FERC is proposing to give LNG plants advance approval to expand later, without full environmental review and limited public input. Companies could add storage tanks, gas processing equipment, pipeline tie-ins, power plants, and marine vessel docks, including on up to 25 acres next to the plant, without FERC ever taking a close look at the specific project. Some work would only be reported after it’s finished, and the public would have less opportunity to give input than they have now and for some activities, it would be too late to influence decision-making.
FERC is proposing a 3-tier process that will allow automatic blanket approval, approval with a 60-day prior notice, and approval with a 90-day prior notice with different allowances under each. But none of the tiers provide the basics that the Natural Gas Act and the National Environmental Policy Act requires – a hard look at the environmental impacts before a project proceeds, informed decision-making, and meaningful public participation. (See 15 U.S.C. § 717f(e); Kleppe v. Sierra Club, 427 U.S. 390, 410 (1976); 40 C.F.R. §§ 1501.9(e), 1508.1(g) (CEQ regulations; and Baltimore Gas & Elec. Co. v. NRDC, 462 U.S. 87, 97 (1983)).
Why it’s a problem
- FERC already has a very limited environmental review process. They want to “streamline” and “speed up” reviews, making a poor process even worse, risking greater environmental and public health harm
- Public input would be limited, opportunities for comment would be reduced, and the scope of some project activities would be obscured
- Each project has a proposed size limit, but nothing limits how many times a plant can expand. One FERC commissioner warned that a plant could, in theory, “double in size or more this way.”
- LNG is a hazardous, highly flammable, and potentially explosive substance and the plants are dangerous.
- LNG processing pollutes. Nitrogen oxides (NOx), Particulate Matter, volatile organic compounds and other toxic and health-harming pollutants are released into the environment during the liquefication process, burdening local and regional communities.
- Expansions could incrementally increase harmful air emissions without consideration of the cumulative effects
- Methane, a singularly powerful greenhouse gas, is released to the atmosphere through LNG processing, storage, and transport, worsening the climate crisis. The climate harms of a project are now required to be considered by FERC but blanket authorizations would further entrench the Commission’s historic failure to adequately address them by shielding LNG related activities from project specific scrutiny. Climate impacts are cumulative by nature and cannot be meaningfully addressed through generic assumptions.
- Expansions could bring more and bigger LNG tankers on our rivers, with no limit by FERC.
- Local safety officials would be sidelined. Instead of working with the state and local emergency responders, companies would only have to notify them, not consult with them.
The Delaware River is a target for LNG export development – two export projects are being proposed. We need FERC to tighten the environmental review process, not loosen it.
!! Be sure to reference the appropriate docket number when submitting your comments:
Docket No. RM26-2-001 !!
Step-by-step instructions for using FERC e-Comment:
- Go to FERC Online e-Comment web page: https://ferconline.ferc.gov/QuickComment.aspx
- Enter the required information into the online form.
- You will receive an e-mail from FERC.gov with a special confirmation link. Click this link to go back to the e-Comment portal.
- Enter the docket number RN26-2-001 into the search box and click “Search”. Click the blue plus sign (+) to the right of the docket that appears to select it for your comment.
- Enter your comment of up to 10,000 characters in the provided box. Feel free to use any of the sample comments below as a starting point.
- Giving a personal touch to your comment can be more effective
- Click the “Send Comment” button to submit. You should see a screen saying that you have successfully submitted a comment and you will receive an email confirming your submission.
Sample Comments:
Sample #1:
I am submitting these comments on Docket No. RM26-2-001 to the Federal Energy Regulatory Commission because […something about yourself, your concerns, your experiences]
I oppose FERC’s proposal to let plants expand through a “blanket authorization” that would remove a full review of certain LNG projects and reduce public scrutiny to “streamline permitting” and “speed energy infrastructure development” for applicants. LNG plants are dangerous and polluting, and FERC has said before that each expansion needs its own careful review. This proposal would allow new storage tanks, processing equipment, and marine vessel docks, and more and bigger LNG tanker ships, endangering people and the environment. New pipeline tie-ins, power plants, and water systems could be added, some without prior notice – it would just be reported after the expansion was done. And despite acreage limits for expansion, nothing restricts how many times a plant can expand. One FERC commissioner warned that a plant could, in theory, “double in size or more this way.” (See NOPR, 197 FERC ¶ 61,036 (2026): paras. 22 and 44–45 (automatic and 60-day tiers); paras. 56 and 59–61 (90-day tier and 25-acre limit); paras. 23 and 65 (no cost limits); para. 115 (environmental review for prior notice projects); para. 8 (Chang, Comm’r, concurring) (“double in size”).
This would limit the opportunities for the public to provide input into the activities undertaken under the new process, even though they could be directly affected. It would also cut out state and local emergency responders from giving input and receiving necessary training or equipment before the activities are fait accompli.
Communities along rivers and coasts, including the Delaware River where LNG projects are proposed, deserve and require a full environmental review and a meaningful public process. I request FERC withdraw this proposed rulemaking.
Sample #2:
I am submitting these comments on Docket No. RM26-2-001 to the Federal Energy Regulatory Commission because […something about yourself, your concerns, your experiences]
I oppose FERC’s proposal to let plants expand through a “blanket authorization”.
The proposed 3-tier blanket authorization process would eliminate the ability to accurately assess climate impacts. Climate impacts require a comprehensive analysis of greenhouse gas emissions from a cumulative cradle-to-grave approach, which can’t be accomplished under this truncated process. To meaningfully evaluate climate change impacts associated with LNG projects, including direct, indirect, and cumulative greenhouse gas emissions resulting from natural gas combustion, as is required, will not be possible if project specifics are not comprehensively examined. (See 867 F.3d 1357, 1373–74 (D.C. Cir. 2017)). More recently, the court reiterated that upstream and downstream emissions must be considered in NEPA review. (See Birckhead v. FERC, 925 F.3d 510, 518–19 (D.C. Cir. 2019)).
Communities along rivers and coasts, including the Delaware River where LNG projects are proposed, deserve and require a full environmental review and a meaningful public process. I request FERC withdraw this proposed rulemaking.
Sample #3:
I am submitting these comments on Docket No. RM26-2-001 to the Federal Energy Regulatory Commission because […something about yourself, your concerns, your experiences]
I oppose FERC’s proposal to let plants expand through a “blanket authorization”.
The processing, storage, and transport of LNG releases pollution every day of operation. Nitrogen oxides (NOx), Particulate Matter, volatile organic compounds and other toxic and health-harming pollutants are released into the environment during the energy-intensive liquefication process, burdening local and regional communities.
LNG is dangerous, highly flammable, potentially explosive, and a classified hazardous substance. (See https://bit.ly/4ACIdU7 and https://bit.ly/PGWLNGSafetyData). LNG plant and infrastructure operations are difficult to safely manage, requiring close scrutiny of any expansion, despite FERC’s claim that the proposed automatic authorization projects are “so well understood”. Accidents and fires do occur for activities that would potentially be covered by automatic authorization, as recently as 2022 in Texas. (See https://www.eia.gov/todayinenergy/detail.php?id=52859)
Communities along rivers and coasts, including the Delaware River where LNG projects are proposed, deserve and require a full environmental review and a meaningful public process. I request FERC withdraw this proposed rulemaking.